Depending on the nature of the land, there will be soil testing, site-leveling and clearing shall be undertaken prior to starting the actual construction.

As the name suggests, this is simply just done when the foundation is laid. It includes measuring out the design on the site, pouring the footings, under slab drainage, moisture barrier and special mesh for termite protection.

It includes the installation of internal and external support structure along with walls, conduit for electrical and plumbing, the roof frame and sheeting, gutters and insulation.

At this point where literal start “locking up” the property because the windows, doors and remaining walls will be installed. Making safety for plumbers, electricians, cabinet makers and other tradesman to begin fitting out the property.

Plumbing, Electrical (including lights and power points), other fixtures and fittings will be installed. The design features that make the property as a home will also be added such as cornices, tiling, cabinets and shelving and architraves.

This is basically where all painting, installations and detailing shall be completed and effectively ready to move in

It depends on the size and design of the build but generally:

  • The slab or base stage: 1-2 weeks
  • Frame stage: 3-4 weeks
  • Lockup stage: 4 weeks
  • Fit-out or fixing stage: 5-6 weeks
  • Practical completion stage: 7-8 weeks